Temperature limits
Fendolite-MIIAir and steel at least 4°C, or 2°C and rising. Maximum 50°C.
PSK-101Air and steel at least 4°C, or 2°C and rising. Maximum 45°C.
Topcoat 200Air and surface at least 5°C and rising. Maximum 40°C.
All threeThe surface must be at least 2°C above the dew point.
Working through winter
- Sheet in the work area with industrial quality sheeting.
- Heat the enclosure to the conditions above.
- Apply PSK-101 and hold the conditions for 24 hours. Store PSK-101 indoors so it cannot freeze.
- Fix the mesh. The temperature can be allowed to drop while this is done.
- Bring the temperature back up, then mix and spray. Mixing water should be above 4°C and can be warmed to 35°C.
- Hold the conditions for at least 48 hours, then keep the work above freezing for a further 72 hours.
Fendolite holds more water in winter, and more again inside an enclosure with little air movement, so it takes longer to dry before the topcoat can go on.
Before the topcoat
Topcoat 200 is applied once the Fendolite has dried. Promat give a moisture meter reading for this, taken with a Protimeter Timbermaster at least five days after spraying. There must be no dew, condensation or rain on the surface, and the work is protected from the weather for 24 hours before and after painting.